Earith Road:
Traffic management: Traffic control (two-way signals)
Date: Jun 5 – Jun 22
Description: REPLACE APPROX. 320M OF 4″ CI WITH 90MM AND ANY ASSOCIATED SERVICES
Location: O/S 6 TO O/S 70 EARITH ROAD
Here at Cadent, we look after the gas pipes in your area. We make sure the pipes that bring the gas to your home keep you safe, warm and connected. We’re replacing the old pipes with new plastic ones which will mean that you’ll be ready for greener gas in the future. We’ll have to turn off your gas supply during some of our works and may need access to your home, but our teams on site will be on hand to let you know more information.
Rockmill End:
Traffic management: Traffic control (two-way signals).
Date: Apr 15, 9:05 AM – Jul 28, 5:00 PM
Description: S278 works to the site entrance. Includes new carriageway, resurfacing existing, new drainage.
Location: New Site, Meadow Road jnc Sponge Drove/Rockmill End, Willingham, CB24 5JL.
Carriageway resurfacing being carried out to improve road safety and quality of travel.
Station Road:
Traffic management: Traffic control (two-way signals)
Date: Jun 9 – Jun 18
Description: facilitate the installation of a new sewer connection
Location: Land adjacent to Ryecroft
Installation of apparatus that belongs to a Third Party
Fen End:
Traffic management: Road closure
Date: Aug 21 8:00 AM – 6:00 PM
Description: Connections Small Works: Install / Replace / Remove / Disconnect underground service cables: ROAD CLOSURE FOR IVY CLEARANCE ON POLE
Location: ROAD CLOSURE REQUIRED OUTSIDE 20B FOR IVY REMOVAL FROM POLE AND DISCONNECTION
Priest Lane
Traffic management: Road closure
Date: Jun 9 – Jun 27
Traffic restrictions: Jun 9 – Jun 27: Detour