Bar Hill junction roundabout (over the A14)
The lane drop around the gyratory is scheduled to be in place for another few weeks. The electrical items we’re awaiting to be delivered are scheduled to arrive early September. Once fitted, these electrical items will be tested to ensure compliance and safety. Once completed, the cones here can be removed.
Bar Hill junction roundabout to Saxon Way/ Crafts Way roundabout – downhill
The lane drop here will be in place until we have been able to install fencing. The closure of suppliers during the pandemic has meant the original fence type as per the design is not available and we are reviewing alternatives. As a consequence, unfortunately we’re unable to confirm when these cones will be removed. We are actively chasing suppliers to resolve this as quickly as possible.
Saxon Way/Crafts Way roundabout to Bar Hill junction roundabout – uphill
The lane drop here is in place for access to ongoing drainage works, followed by completion of the landscaping. The recent storms has meant this work has taken slightly longer than originally planned and currently we anticipate this work will be completed early October.
All works are currently due for completion at Bar Hill early October and we will provide you with a further update at the end of September.
Kind regards
A14 Cambridge to Huntingdon improvement scheme